The objective of this project is to add PIT Tag detection to the center and right fish ladders at the Chandler diversion dam, Prosser Wa.

Pictures

Pictures


Journal

PRO Center Ladder

Darren Chase 11/08/05 10:18 PM

The BOR mechanics have investigated the counting window and are using an outside source to try and fix the leaking without removing the window. I spoke with Richard Corkins (BOR) on 11-8-05 and the outside source has not had a chance to repair the window. It is speculated that the window will be repaired some time next week. Once the window is repaired PSMFC will run a water up test.


Center Ladder completion

Darren Chase 10/27/05 08:49 AM

The center ladder construction and detection installation have been completed. Mark Johnstone(YIN), Dave Knight(Knight Construction), and Darren Chase(PSMFC) did a final walkthrough yesterday to inspect all the construction. Dave Knight had to finish a small grouting job but the construction was signed off by all parties concerned.


Construction Completed

Darren Chase 10/11/05 04:09 PM

The work performed by Knight Construction was completed on 9-30-05. A walkthrough was done on 10-3-05 which included Mark Johnstone (YIN), Don Warf (PSMFC), Richard Corkins (BOR) to inspect the work. There were a couple of small items that Mark Johnstone noted and will have Knight finish the work. The BOR responsibilties have not yet been completed but should be done by the end of this month.


FW: Right Bank Fish Ladder design drawings for review

Darren Chase 09/15/05 09:10 AM


Darren R. Chase
PSMFC
Systems Engineer
(509) 735-2773 ext.3
darren@psmfc.org



Original Message-----

From: David Knight [<a href="mailto:dave@knightconst.com">mailto:dave@knightconst.com</a>]
Sent: Monday, July 11, 2005 11:08 AM
To: 'Mark Johnstone'
Cc: 'Don Warf'; darren@psmfc.org; scott_livingston@psmfc.org
Subject: FW: Right Bank Fish Ladder design drawings for review

Attached is the preliminary drawings for Prosser. Please review and get back
to me ASAP on any comments. We are planning to mobe on Monday the 18th. If
you have any questions please get back to me at 509-276-2229.

Thanks
David Knight


Original Message-----

From:
Sent: Friday, July 08, 2005 4:48 PM
To: dave@knightconst.com
Cc: Tara Silverblatt (E-mail); Dale Miller (E-mail); Dan Russell (E-mail)
Subject: Right Bank Fish Ladder design drawings for review

Dave,

Here are the Right Bank Fish Ladder design drawings for review. Please note
that the antenna wall guide drawing sent to you previously was renumbered.
Some additional information was provided on the revised sheet. However, the
original profile and length of the guide did not change.

Have a great weekend,


1-R.pdf
2-R.pdf
3-R.pdf
4-R.pdf
5-R.pdf
6-R.pdf
7-R.pdf
8-R.pdf
9-R.pdf
10-R.pdf



FW: Antenna delivery

Darren Chase 08/09/05 09:25 AM

Darren R. Chase

PSMFC

Systems Engineer

(509) 735-2773 ext.3

darren@psmfc.org


From: Mark Johnston [1]
Sent: Monday, July 18, 2005 10:45 AM
To: darren@psmfc.org
Subject: Re: Antenna delivery


Darren,

as you can see I received your e-mail

Later,

Mark

Darren Chase wrote:

<p><u1:SmartTagType namespaceuri="urn:schemas-microsoft-com:office:smarttags" name="City" downloadurl="http://www.5iamas-microsoft-com:office:smarttags"><u1:SmartTagType namespaceuri="urn:schemas-microsoft-com:office:smarttags" name="place" downloadurl="http://www.5iantlavalamp.com/"></u1:SmartTagType></u1:SmartTagType>Biomark delivered four (4) of the five (5) antennas and transceivers to the PSMFC Kennewick office on Tuesday. We will be running tests in the lab prior to delivery when need for installation. The fifth transceiver and antenna is scheduled to be delivered on 7-27 or 7-28-05 to the Kennewick office.<u1:p></u1:p>

<u1:p></u1:p>

Darren R. Chase<u1:p></u1:p>

PSMFC<u1:p></u1:p>

Systems Engineer<u1:p></u1:p>

(509) 735-2773 ext.3<u1:p></u1:p>

<u1:p></u1:p>

FW: Project start

Darren Chase 08/09/05 09:25 AM

Darren R. Chase

PSMFC

Systems Engineer

(509) 735-2773 ext.3

darren@psmfc.org


From: David Knight [2]
Sent: Tuesday, June 28, 2005 2:06 PM
To: darren@psmfc.org; 'Mark Johnstone'
Cc: 'Don Warf'; rcorkins@pn.usbr.gov
Subject: RE: Project start


I have just talked to my supplier, and he said that he will be able to get the materials to me the week of the 11th. We should to be able to mobe that same week. I will shoot for the 13th. If this changes I will contact you.

Thanks

David Knight


From: Darren Chase [3]
Sent: Monday, June 27, 2005 8:14 AM
To: Mark Johnstone
Cc: Don Warf; rcorkins@pn.usbr.gov; dave@knightconst.com
Subject: Project start


Mark,

I am just touching base with you and everyone else on the project start date and actions. I have it set that Dave will mobilizing on the week of the 4th of July and starting the project with the left ladder modifications the week of the 11th. I was also wondering if there are any drawings on the exact details for the modification? If there is could we get a copy of them, also are there any drawings for the work to be done on the center and right bank ladders, we have not seen anything in the way of project drawings. If my dates are not correct please let me know. If you have any drawings we would really like to have a copy.

Thanks,

Darren R. Chase

PSMFC

Systems Engineer

(509) 735-2773 ext.3

PRO site configuration

Darren Chase 08/09/05 08:24 AM

The completion of the Prosser ladders is scheduled for September 30th. We will need to think about site configurations before this is complete. The coil I.D.’s for the center ladder will be 03, 04 and the right bank ladder will be 05, 06. I will not have communications until late September.

Darren R. Chase

PSMFC

Systems Engineer

(509) 735-2773 ext.3

darren@psmfc.org

Project update

Darren Chase 07/29/05 04:20 PM

This is an update to the installation of the antennas on the Right Bank and Center ladders.


Project Update.doc


Right Ladder Construction Update

Darren Chase 07/22/05 04:14 PM

Construction began on 7-18-05. Knight construction is currently scheduling to work Monday through Thursday 10 hrs. a day. I will be checking on the site on a daily basis when possible. Corkie from the BOR also works Monday though Thursday 10 hrs. A day and has started with the removal of unnecessary equipment.


Antenna delivery

Darren Chase 07/14/05 03:25 PM

Biomark delivered four (4) of the five (5) antennas and transceivers to the PSMFC Kennewick office on Tuesday. We will be running tests in the lab prior to delivery when need for installation. The fifth transceiver and antenna is scheduled to be delivered on 7-27 or 7-28-05 to the Kennewick office.

Darren R. Chase

PSMFC

Systems Engineer

(509) 735-2773 ext.3

Phase 2 project noise test results

Darren Chase 06/28/05 09:23 AM

This is the results of the noise test conducted on the Center and Right Bank ladders.

Darren R. Chase

PSMFC

Systems Engineer

(509) 735-2773 ext.3


Phase two noise test results.doc


Prosser Dam Adult Antenna Phase Two Project Plan

Darren Chase 06/10/05 11:25 AM

This is the project plan for the construction and installation for the remaining two ladders at Chandler Dam.

Darren R. Chase

PSMFC

Systems Engineer

(509) 735-2773 ext.3


Prosser Dam Adult Antenna Phase Two Project Plan.doc


Listening post configuration

Alan Brower 05/27/05 10:21 AM

On 5/24/2005 I configured the listening posts to create one file per day,
with noise reports generated every two minutes. I also set the clocks to
daylight savings time. These changes will simplify data analysis.



Meeting Minutes

Kick Off Meeting Minutes

Don Warf 05/13/05 01:50 PM


ProsserXDamXMeetingXMinutes5_11_05X_2_.pdf


Links